Dayton-Xenia Road Construction Update
Just heard back from the city with an update on the road work and closure.
At this time it looks like the road will not be closed until after June 1. Until then, there will be periodic disruptions, but no closures.
The gas lines are just starting to be relocated, which will take about a month.
Near the end of April, the electric, phone and fiber lines will be relocated which will also take about a month.
Once that is accomplished the road will be closed for a period of about ten days at the eastern corner of our property. This is to replace the culvert for the creek that runs through our property. After that, at least one lane of traffic, and usually 2, will be open, but with periodic delays.
In the meantime, if you would like to know the road conditions at the moment for a planned trip to visit us, just call our office and we will walk outside and give you as much of an update as we can see in both directions.
Think Spring!
Hope to see you soon.